Active

Remote ID
1
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.13
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Feasibility (S2B). Egypt-Libya grid agreement July 2024. 165 km at 500/400 kV. 1,000 MW transfer. EIRR 12-15%.
Description

165 km AC transmission from Saloum (Egypt) to Tobruk (Libya). 500/400 kV with back-to-back converter station. 1,000 MW transfer capacity. First stage of North African regional electrical interconnection. Egypt and Libya agreed to boost grid connection July 2024. Implementation by Egyptian Electricity Transmission Company and General Electricity Company of Libya.

Capex Cost
300.00USD million
Preparation Cost
15.00
Revenue Model
Transmission tariffs and wheeling charges for power exchange
Project Risk

Political risks due to Libya instability; Technical coordination; Construction delays; Security considerations

Countries
Egypt, Libya
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.06
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Structuring (S3A). Sudan conflict major constraint. 500kV 2,000 MW transfer. EIRR ~16%. BCR 1.8:1.
Description

High-voltage ~400 km 500kV transmission line from Guba (Ethiopia) to Khartoum (Sudan). Part of Eastern Africa Green Power Transmission Network. Enables power trade leveraging Ethiopia hydropower including GERD. Transfer capacity 2,000 MW. Sudan conflict since April 2023 significantly complicates advancement.

Capex Cost
850.00USD million
Preparation Cost
25.00
Revenue Model
Transmission tariffs with bilateral cost and revenue sharing
Project Risk

Geopolitical factors; Sudan conflict since April 2023; Difficult terrain; Cross-system coordination

Countries
Ethiopia, Sudan
Stakeholders
East African Community
Common Market for Eastern and Southern Africa
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.10
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Feasibility (S2B). Binational agency ADCC established. Dam 65-70m. 600 MW. EIRR 13-16%. FIRR 8-10%.
Description

600 MW hydroelectric on Dja River at Cameroon-Congo border. 65-70m concrete gravity dam. Managed by Binational Agency ADCC. Tractebel Engineering technical advisory. Power supply to industrial centres and underserved communities in both countries.

Capex Cost
2,009.00USD million
Preparation Cost
35.00
Revenue Model
Binational PPAs with ENEO (Cameroon) and SNE (Congo) with cost/benefit sharing
Project Risk

Complex binational coordination; Geopolitical factors; Remote location; Biodiversity impacts; Financing complexity

Countries
Cameroon, Republic of Congo
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.09
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Feasibility (S2B). Booue 200-220 MW; Tsengue-Leledi 150-180 MW. 300 km 225kV transmission. EIRR 12-15%. FIRR 8-10%.
Description

Two major hydroelectric sites on Ogooue River in Gabon. Booue: 200-220 MW; Tsengue-Leledi: 150-180 MW. Combined 350-400 MW. Reduces Gabon dependence on thermal generation. Ministry of Energy and Hydraulic Resources (Gabon) and Gabon Power Company (GPC). ~300 km associated 225kV transmission lines.

Capex Cost
1,784.10USD million
Preparation Cost
28.00
Revenue Model
Long-term PPAs with SEEG as primary offtaker, with direct sales to major industrial customers
Project Risk

Hydrological variability; Geological challenges; Cost escalations for remote sites; Dam and transmission coordination

Countries
Gabon
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.17
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Feasibility (S2B). 60 MW total. USD 408M sequential / USD 358.4M simultaneous. Serves 6M+ across CAR, Congo, DRC. EIRR 8-10%.
Description

Hydroelectric development on Lobaye River in SW Central African Republic, 100 km from Bangui near M'baiki. BAC and LOTEMO sites with 60 MW total. Transmission to connect with Chad, Congo, DRC. Post-conflict context with severely underserved electricity supply. USD 408M if sequential, USD 358.4M if simultaneous development. Serves 6+ million people.

Capex Cost
406.50USD million
Preparation Cost
2.00
Revenue Model
Power sales to national utility and neighbouring country utilities
Project Risk

CAR political instability; Financing challenges; Remote location; Security considerations

Countries
Central African Republic, Chad, Republic of Congo, Democratic Republic of Congo
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.02
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Feasibility (S2B). EU and AfDB grants supporting preparation. Run-of-river 287 MW. Annual generation 1,300-1,500 GWh.
Description

The Ruzizi IV (287 MW) power plant project is located on the Ruzizi River, which forms a common border between Rwanda and DRC to the north, and between DRC and Burundi to the south. Managed by Energie des Pays des Grands Lacs (EGL) under CEPGL. Preparation financed by EU (EUR 8M), AfDB/NEPAD (EUR 889K), and CEPGL contributions. Run-of-river configuration. Expected annual generation 1,300-1,500 GWh.

Capex Cost
712.00USD million
Preparation Cost
10.00
Revenue Model
Long-term PPAs with national utilities of Burundi, DRC, and Rwanda
Project Risk

Coordination across three countries; Security in eastern DRC; Technical challenges on Ruzizi River; Hydrological variability

Countries
Burundi, Democratic Republic of Congo, Rwanda
REC
CEEAC-ECCAS
Stakeholders
Economic Community of Central African States
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.11
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Structuring (S3A). CAPACITY: 881 MW (updated from 600 MW). AfDB SEFA USD 800K Jul 2025. Impl Agreement signed. EIA for regulating dam Q2 2025-Q2 2026. Next: EPC award.
Description

Binational Angola-Namibia hydropower on Kunene River, situated 185 km downstream of Ruacana. CAPACITY UPDATED: 881 MW (increased from original 600 MW estimate; confirmed NamPower Chief Commercial Officer Fritz Jacobs, August 2025). Main Dam: 860 MW Francis Turbines; Regulating Dam: 21 MW S-type Kaplan. 50:50 Angola-Namibia split (440.5 MW each). Implementation Agreement signed and approved by both Angola and Namibia cabinets. July 8 2025: AfDB SEFA approved USD 800,000 preparatory grant for FEED and ESIA studies — advancing toward bankability and procurement readiness. EIA for regulating dam commissioned Q2 2025–Q2 2026. Road and grid access studies approved. PJTC and Baynes PIU coordinate implementation. NamPower (Namibia) and RNT (Angola) are implementing utilities. PJTC Co-Chairman Namibia: Simeon Negumbo (Executive Director of Energy). Next step: Award EPC contract and mobilise construction financing.

Capex Cost
1,300.00USD million
Preparation Cost
25.00
Revenue Model
Pari Passu revenue model with equal sharing between Angola and Namibia
Project Risk

Construction and forex risks; Tariff path uncertainty; Resettlement challenges; Environmental flow requirements on Kunene River

Countries
Angola, Namibia
REC
SADC
Stakeholders
Southern African Development Community
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 18 March 2026
PIDA Code
E.30.08
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Hydro Power Plant
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Project Structuring (S3A). ICC arbitration still ongoing Mar 2025. FEC re-awarded CCECC Aug 2024. No construction. 3.05 GW, 12 turbines. Annual 5.457 billion kWh. Target: 2030.
Description

3.05 GW hydroelectric facility on Dongo River near Baruf, Kakara Village, Taraba State, Nigeria. Four dams and two underground powerhouses with 12 turbine generator units. Annual generation 5.457 billion kWh. Nigeria Federal Ministry of Power under Minister Hon. Adebayo Adelabu. Up to 50,000 local jobs during construction. ICC arbitration by Sunrise Power and Transmission Company (SPTCL) against Federal Government ongoing as of March 2025. ICC ruled against FG objections October 13 2022. FG and Sunrise signed settlement in January 2020 but FG failed to make payments. August 2024: FEC re-awarded USD 5.8B contract to CCECC consortium (China Energy Engineering Corp.) despite ongoing ICC proceedings. EFCC declared Sunrise chairman Leno Adesanya wanted February 2024. Construction surveys begun late 2020 but stopped 2022 — contractors unpaid. Power Minister Adelabu announced equipment mobilisation targeting 2030 completion. No ground-breaking as of March 2026.

Capex Cost
5,800.00USD million
Preparation Cost
50.00
Revenue Model
PPAs with Nigerian Bulk Electricity Trading Company and regional off-takers
Project Risk

ICC arbitration ongoing; Financing challenges; No construction as of 2026; EFCC corruption proceedings; Construction surveys halted 2022; Political risks

Countries
Nigeria
REC
ECOWAS-CEDEAO
Stakeholders
Economic Community of West African States
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 17 March 2026
PIDA Code
E.30.05
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Energy
Subsector Name
Power Interconnector
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Project Structuring (S3A). AfDB updating feasibility/ESIA Jan 2024. ESIA complete BNZ; Zambia ongoing. 400kV, 300 MW initial to 600 MW. DBSA USD 50M; AFD USD 30-50M; AfDB 40% debt committed.
Description

New 400 kV transmission facilities in Zimbabwe, Zambia, Botswana and Namibia creating an alternative power corridor in SAPP. Initial operation at 330kV targeting 300 MW transfer, upgradeable to 600 MW at 400kV. Decongests existing central corridor. AfDB procured consultancy to update feasibility and ESIA studies January 2024. ESIA complete in Botswana, Namibia, Zimbabwe; Zambia ESIA by SWECO ongoing. Fichtner (Germany) provides transaction/technical advisory; PhD Capital (South Africa) provides project coordination. Four national utilities: NamPower, ZESA, ZESCO, BPC — each 20% equity in SPV incorporated in Namibia. Development banks interested: DBSA (USD 50M pledged), AFD (USD 30-50M pledged), AfDB (40% of debt financing committed).

Capex Cost
240.00USD million
Preparation Cost
10.00
Revenue Model
Transmission tariffs and wheeling charges for power trading
Project Risk

Four-country coordination; Financing risks; Construction delays; Regulatory harmonisation

Countries
Comoros, Zambia
REC
SADC
Stakeholders
Southern African Development Community
Start Date
Date Created Raw
Updated Date
By Anonymous (not verified) , 17 March 2026
PIDA Code
W.30.11
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
Water
Subsector Name
Water Supply
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Project at Pre-feasibility Stage (S2A). Project preparation phase January-November 2025 as per project schedule. Construction targeted for May 2026-October 2027. Madagascar national project under Ministry of Water, Sanitation, and Hygiene.
Description

Development of water infrastructure and resource management interventions in Antanambao Manampotsy area of Madagascar. The project uses a cascading lakes and retention dams system to improve access to clean drinking water, protect community water sources, implement climate adaptation measures, and support agricultural productivity for 71,910 residents in the project area. Project timeline: preparation January-November 2025; procurement December 2025-April 2026; construction May 2026-October 2027.

Capex Cost
88.00USD million
Project Risk

Implementation and coordination risks

Countries
Madagascar
Stakeholders
Sudan Ministry of Water Resources
Irrigation and Electricity
Zambia - Ministry of Water Development
Sanitation and Environmental Protection
Start Date
Date Created Raw
Updated Date