This is a multi-country regional project managed by CICOS to unlock the economic potential of the Congo Basin's extensive inland waterways. It is currently in the Project Definition stage (S1), having advanced from Enabling Environment in 2024. The project faces significant implementation challenges, including the security situation in eastern DRC and complex multi-country coordination, reflected in its 'Red' traffic light status. Total project cost is estimated at USD 93.8 million, with a financing structure of 90% grant funding and 10% national contributions. A preparation cost of USD 5 million is identified, with a USD 2.5 million funding gap.
<p>Construction of 122km / 400 kV section of the ZTK transmission interconnector from Mbeya (Tanzania) to Tunduma (border with Zambia).</p>
Description
<p>Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 400kV, 292km Iringa - Kisada - Mbeya transmission line, 122km of 400kV Mbeya - Tunduma transmission line and 4km of 400kV transmission line from Tunduma to Border of Zambia. </p>
Capex Cost
123.00USD million
Preparation Cost
24.00
Operation Cost
2.46
Project Risk
<ul>
<li>Environmental Risks: Minimal Social Risks: Minimal Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported</li>
</ul>