Feasibility (S2B). Sanankoroba 150 MW construction began May 2024. Three sites: Fana, Bougouni, Sanankoroba. 498 GWh/year. IRR 12-15%.
Description
WAPP implementation strategy for integrated West African electricity market. Utility-scale solar PV across three sites: Fana, Bougouni, Sanankoroba. 150 MW total. Annual production 498 GWh. Construction began on 150 MW Sanankoroba plant May 2024. Increases renewable energy (Solar, Wind) in regional energy mix.
Capex Cost
250.00USD million
Preparation Cost
5.00
Revenue Model
Long-term PPAs with national utility and WAPP
Project Risk
Security risks; Financing challenges; Grid integration; Land use management; Mali political instability