Extension of the Tanzania National ICT Broadband Backbone (NICTBB) southward to connect with Mozambique, enabling access to the EASS and SEACOM submarine cables landed in both countries and creating resilience in international connectivity. The project uses Single Mode Optical Fiber type G652D with OTN over DWDM transmission technology. It also encompasses the extension of the NICTBB westward across Lake Tanganyika to Kalemie in DRC (see I.02.30.10 for the separate DRC component). Tanzania has approved the tender document and construction preparations are advancing. Total project investment estimated at USD 60 million.
PIDA Code
I.02.30.08
Project Status
Active
Project Stage
Transaction Support & Financial Close
Completion Percentage
0
Sector Name
ICT
Subsector Name
Fibre Optic Cable
Alternative Names
NICTBB-Mozambique; Tanzania-Mozambique Fiber; SEACOM-EASS Interconnect
Reference Plan
PIDA PAP 2
On SDM
Off
Summary
Tanzania tender document approved — construction preparations underway. July 2025: Tanzania Minister confirmed the country is now digitally linked to six neighbours including Mozambique. The Kenya-Tanzania cross-border terrestrial fiber link launched July 18, 2025 at Lunga Lunga/Horohoro further strengthens the regional connectivity architecture this project contributes to.
Description
Capex Cost
4.00USD million
Revenue Model
Infrastructure access fees and international connectivity services to carriers
Project Risk
Cross-border implementation and regulatory coordination between Tanzania and Mozambique; Environmental considerations along coastal and inland routes; Long-term operations and maintenance arrangements
Countries
Mozambique, Tanzania
REC
SADC
Stakeholders
Southern African Development Community
Tanzania - Government of Tanzania
Mozambique - Government of Mozambique
Start Date
Date Created Raw
Updated Date
Latitude
-10.680000
Longitude
40.165700