High-voltage ~400 km 500kV transmission line from Guba (Ethiopia) to Khartoum (Sudan). Part of Eastern Africa Green Power Transmission Network. Enables power trade leveraging Ethiopia hydropower including GERD. Transfer capacity 2,000 MW. Sudan conflict since April 2023 significantly complicates advancement.
Capex Cost
850.00USD million
Preparation Cost
25.00
Revenue Model
Transmission tariffs with bilateral cost and revenue sharing
Project Risk
Geopolitical factors; Sudan conflict since April 2023; Difficult terrain; Cross-system coordination